Compare a project to a schedule

Use the
Compare
tab of the
Import Export Manager
to compare the current project to a previously saved schedule file and create a report that highlights the differences.
To compare a project to a saved schedule
  1. Click
    TOOLS > Import Export Manager
    . The most recently used project is opened by default.
  2. To choose a different project to compare with, click
    FILE > Open
    and then select the project from the list.
  3. Click the
    Compare
    tab.
  4. In
    Excel File
    , type the name of the schedule file to use for comparison or click the ellipsis to browse to the schedule file.
  5. (optional) Select
    Only Show Changes
    to limit the content of the comparison report to items in the current project that differ from the schedule.
  6. Click
    Compare
    .
    The comparison report opens in Excel.
  7. Click
    Finish
    to close the
    Import Export Manager
    .
Provide Feedback
Have questions or feedback about this documentation? Please submit your feedback here.