Process Solutions

Process Solutions

Device Integration

Field Device Testing Procedures

The Interoperability testing procedures below are followed for each field device and the results recorded in a test report for integration planning purposes.
  1. Install the Third Party Device in an operating H1 network.
  2. Change the BOF Class of the device.
  3. Assign a tag to the device.
  4. Add function blocks to device.
  5. Perform download operations.
  6. Set device to factory defaults.
  7. Configure function blocks.
  8. Export tags.
  9. Create a Control Module and add function blocks and links to the Linking Device.
  10. Verify device operation — monitor link values.
  11. Verify device operation — UPDATE Command.
  12. Verify that a device can bridge across H1 channels in the same FFLD.
  13. Verify that a device will operate with the AB CN2FF module.